| Bow Hill Road Reconstruction Concrete -Sauk Valley Road Farm to Market Road / Josh Wilson Road Intersection Improvements Francis Road Reconstruction: Section 1 Garden of Eden Rd/Willard Creek Culvert 2021 HMA Overlay Project Josh Wilson Road: Phase 1 North Shore Drive Roadway Repair Sinclair Dock Replacement Sinclair Island Marine Access Upper Finney Creek  Bridge (Seismic Retrofit)
 |             Josh Wilson Road – Phase 1 Project | Completed April 22, 2022ES33000-9
Josh Wilson Road – Phase 1 Project: Closure Update Road  Closure Josh Wilson Road: Will remain closed to traffic until the evening of  Tuesday, September 21st between Avon Allen Road and Jensen Lane: 
            The       contractor will begin paving the roadway on Monday 9/20 thru 9/24 at Josh       Wilson Road.Josh       Wilson Road will be open to 2-lane traffic on the evening of Tuesday,       September 21st and will remain open to 2-lane traffic in the       evenings until the completion of the project on October 1, 2021.During       the day Josh Wilson Road will be flagged with 1-lane traffic only       beginning the day on Wednesday, September 22 until the completion of the       project. Project DescriptionSkagit  County has contracted with Interwest Construction Inc. for the Josh Wilson Road  – Phase 1 Project. The project will consist of reconstructing a portion of Josh  Wilson Road from Avon Allen Road to the west of Jensen Lane (1.1 miles),  widening of the existing roadway (11-ft wide travel lanes with 4-ft shoulders)  to meet current County road standards (12-ft wide travel lanes with 8-ft  shoulders). Project will also stabilize road base, replace an existing culvert,  and the addition of guardrail along both sides of road.
 Funding Sources: 
            FHWA  Surface Transportation Program (SCOG)      $1,342,552Rural  Arterial Program (CRAB)                                  $1,000,000Skagit  County Road Fund                                          $1,900,000 Total Project Cost:                                                      $4,242,552           Project Update as of July 30, 2021:
 Full  Road Closure Schedule:
 Full road closure will begin on or  around August 9th through September 17th, 2021 for the  following construction activities:
 
            Installing       temporary traffic signs & devices in the areaTransferring       overhead utilities Removal       of existing pavement, grading roadwayPlacing       streambed gravel, gravel base, and crushed surfacing Installing       new storm filtration system, catch basins, culverts, and guardrailHot       mix asphalt paving and striping the roadway Removal       of a failing arched corrugated metal pipe Installation       of precast concrete box culvert and retaining walls to improve drainage. 
 
 Full  road closure is necessary during construction to allow adequate space for the  contractor to install the various project elements. Although the road closure  is a few days longer than originally planned the overall inconvenience of  construction is much shorter.The  Detour Routes for the road closure will be Avon Allen Road and Farm to Market  Road.
 
            Local       access for residents near and on Michael Place will be able to access off       Josh Wilson Road from Avon Allen Road. Local       access for residents near and on Jensen Lane will be able to access off       Josh Wilson Road from Farm to Market Road.  
 Due  to COVID-19 restrictions the County was not allowed to conduct an open-house  meeting for the public as planned.Work  Completed:
 April 19th through May 7th  the contractor installed the preload embankment along the north side of the road  to ensure a stable road base, see exhibit below:  
            By  importing and place gravel base material just north of the shoulder.Install  Pre-Cast Concrete Barriers along the north shoulder of Josh Wilson Road.    
 
            From  May through July the  contractor has been surveying, documenting, and monitoring the thirteen (13)  settlement plates weekly throughout the site to determine the amount of  settlement. The settlement period will be completed the week of August 1st.  For More Information, contact:
 Jennifer Swanson
 360-416-1400
 jennifers@co.skagit.wa.us
 
 | Contact Public Works Engineering Assistant  County Engineer | Engineering Division ManagerThomas  Weller, P.E.
 
 1800 Continental Place
 Mount Vernon, WA 98273
 Phone: (360) 416-1400
 Fax: (360) 416-1405
 
 email: pw@co.skagit.wa.us
 |